Objective of Heat Supply Improvement Project (HSIP) to improve energy efficiency and seismic stability in selected public buildings, mainly, in education and health sectors (for example, in schools, kindergartens, hospitals and clinics).

Project implementation period: 2019 – 2023.

Financing: the source of Project financing is IDA (World Bank) and the Government of Switzerland represented by State Secretariat for Economic Affairs (SECO) of Federal Department for Economy, Education and Research. Total project budget is 12.661 million USD, of which amount of (SECO) Grant: 2.661 million USD; IDA Grant amount: 10.0 million USD.

HSIP covers 7 oblasts and 2 cities, project implementation according to coverage of oblasts was divided into three Cycles:

     Cycle 1: Таlas and Chui oblasts as well as Bishkek city;
     Cycle 2: Naryn, Jalal-Аbad and Issyk-Kul oblasts;
     Cycle 3: Оsh and Batken oblasts, as well as Osh city.

According to project design under the Cycle 1 the retrofitting of six public educational and health buildings was planned. Contract for development of DED for six facilities was signed with design company in May 2020. To date DED for 2 facilities is ready, namely for: 1) Secondary school # 82, housing estate Аlа-Тоо, Lenin rayon, Bishkek city; 2) Secondary school in village Sretenka, Моskva rayon, Chui oblast. On 30.12.2020, a tender was announced for the selection of contractors for retrofits. Based on results of contractor selection the project will proceed with retrofits for two abovementioned facilities. For remaining 4 facilities the project is under preparation of DED.

Selected public buildings in Chui, Таlas oblasts and Bishkek city under the Cycle 1 

#

Name

Oblast

Rayon

Heated area (m2)

1.

General Medical Practice Center

Chui

Panfilov

3413

2.

Kindergarten Kolokolchik

Chui

Моskva

446

3.

Secondary school # 82, housing estate Аlа-Тоо

Bishkek city

Lenin

1184

4.

Secondary school named after А. Soltonov

Таlas

Таlas

1084

5.

Secondary school named after R. Shukurbekov

Таlas

Kara-Buura

1128

6.

Sretenka secondary school

Chui

Моskva

1152

For Cycle 2, a detailed energy and seismic audits of selected public buildings was carried out. Further, according to the results of the audit, the final list of participants' buildings for retrofitting under the project will be identified. Currently, the consulting company is completing the preparation of reports on energy seismic audit. Perhaps the list of buildings to be retrofitted will be changed based on the results of these reports.

Selected public buildings in Jalal-Аbad, Naryn and Issyk-Kul oblasts under the Cycle 2 

#

Name

Oblast

Rayon

Heated area (m2)

1.

Аlа-Buka territorial hospital

Jalal-Аbad

Аlа-Buka

3370

2.

Secondary school # 1 named after Т. Моidunov

Jalal-Аbad

Тоguz-Toro

2999

3.

Rayon territorial hospital

Naryn

Аk-Таlaa

1840

4.

Secondary school # 89 named after P. Zhumanazarov

Jalal-Аbad

Suzak

2371

5.

Gymnasium school named after Т. Тursunbaeva

Naryn

Jumgal

4474

6.

Kindergarten Zhanyl-Мyrza

Jalal-Аbad

Тоguz-Toro

644

7.

Secondary school #15 named after А.Мukanov

Issyk-Kul

Тyup

1044

The Cycle 3 is planned to launch at the beginning of 2021.